Project Timeline

..............................................................................................................
September 2016
Environmental Impact Assessment starts
..............................................................................................................
August 2017
Submission of Scoping Report to Argyll and Bute Council
..............................................................................................................
Autumn 2017 and Spring 2019
Public consultation in the form of two public exhibitions to be undertaken
..............................................................................................................
Winter 2019/20
Submit application for planning permission to Argyll and Bute Council
..............................................................................................................
Winter 2021/22
Anticipated decision on planning application